Aug 12, 2020: No Registration Required for Jumma Salat @ Genesis Centre, Only Savanna Musalla Requires Registration
Aug 12, 2020: : Jumma Schedule, Genesis Centre 1:45 PM/2:15 PM/2:45 PM- Three Salat/ Savanna Musalla 2 PM One Salat Only
July 21, 2020: Eid-Ul-Adha: July 31st 2020: Savanna Musallah: 6:30 AM/7:30 AM- Brothers Only, please follow COVID-19 guidelines- Registration Required For Savanna-Link will be shared on Wednesday 22 July 2020 5 PM Inshallah
June 01, 2020: Alhamdolillah 5 Times Daily Salat started @ Savanna Musalla. No Wudu/Washroom facility available so please come prepared
Maktab Update: Quran Classes will be online using Zoom Application: Please contact Imam Umer for any question at 306-201-7761

Project Expenses

Project Expenses

The Al Hedaya board humbly reminds the community of good news from the prophet (S.A.W.) in a hadith reported by Imam Bukhari and Imam Muslim, Whosoever builds for Allah a masjid, Allah will reward him similar to it in paradise. In another narration reported by Imam Ahmad, Whosoever shares in building a masjid for Allah, even if it is as small as a birds nest, Allah (S.W.T) will buildfor him a house in Paradise. This is the greatest news for a winning investment that is guaranteed byAllah (S.W.T).

Donating money to build a masjid for the sake of Allah is a sadaqah jariah (continued charity), meaning the reward will continue to reach the donor even after his death.

Major Milestones

Rezoning application is currently under review with the city of Calgary, the major milestones of the project are given below:

Project Milestone Timeline Cost(C$)

Millions

Cumulative Cost (C$) Millions
Land Purchased Total Land cost paid off 2010 1.65 1.65
Rezoning application halt due to Area structural plan and storm water not approved 2010-2015
Area Structure Plan for Cell D Approved 2016
Storm water, Traffic, geo-tech & other studies completed August 2016 0.2 1.85
Zoning Application submitted September 2016 0.2 2.05
Approval of zoning from the City in process End of 2017* 0.2 2.25
Development Permit June, 2018* 0.1 2.35
Building Permit September, 2018 0.2 2.55
100% detail design submission January 2019* 0.3 2.85
Tendering March, 2019*
Construction Start June, 2019* 5.5 8.35
Phase1- (Opening of Masjid) 2020* 3.5m 11.85
Phase 2 (Opening of School) 2027* 4.5m 16.35

*Above dates are estimate subject to the City Approvals and funding.